ENDERBY – The second phase of Cliff Avenue construction begins following the Labour Day long weekend. This phase will complete the construction of Cliff Avenue from the Vernon Street intersection to the Bawtree Bridge.
Construction will occur from Sept. 6 to approximately Nov. 11. Works will generally occur Monday to Friday from 7 a.m. to 5:30 p.m., although there may be times when longer hours or Saturday work is required.
During Phase 2 construction, there will be single-lane alternating traffic and no parking within the limits of the works. Two-lane traffic will be provided outside of the limits of the works. During certain activities, detours will be marked.
This exciting project will replace critical underground infrastructure and create a new streetscape that will promote social and economic growth. The general contractor for the Cliff Avenue renewal is Mounce Construction Ltd. During construction, dedicated pedestrian walkways will be available within the limits of the works.
The City provides free parking throughout the downtown core, including nearby parking lots on Mill Avenue, Russell Avenue, and Maud Street.
The City of Enderby thanks the public for their cooperation and courtesy as the second and final phase of the Cliff Avenue reconstruction begins.
News from © iNFOnews.ca, . All rights reserved.
This material may not be published, broadcast, rewritten or redistributed.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Want to share your thoughts, add context, or connect with others in your community?
You must be logged in to post a comment.