PORTSMOUTH, Va. – The watchdog agency for Congress says the Navy’s aging public shipyards are failing to fully meet the military’s needs.
The Virginian-Pilot reported Tuesday that a Government Accountability Office report is sharply critical of the four facilities.
It found that a backlog of projects to maintain and restore ships will take 19 years to clear. The cost of the backlogged projects has grown 41 per cent to an estimated $4.86 billion.
All of the shipyards were built at least a century ago. And they were designed to deal with older vessels, reducing their efficiency.
The four facilities are Portsmouth Naval Shipyard in Kittery, Maine; Puget Sound Naval Shipyard and Intermediate Maintenance Facility in Bremerton, Washington; Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility in Hawaii; and Norfolk Naval Shipyard in Portsmouth, Virginia.
___
Information from: The Virginian-Pilot, http://pilotonline.com
News from © iNFOnews.ca, . All rights reserved.
This material may not be published, broadcast, rewritten or redistributed.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Want to share your thoughts, add context, or connect with others in your community?
You must be logged in to post a comment.