KAMLOOPS - It’s that time of year. Spring officially kicks off March 20, but we’ve been lucky enough to already have several weeks of spring-like weather, allowing crews to get roads cleaned ahead of construction season. Streets Manager Glen Farrow says things are progressing well and crews are ready to move in to the Sahali...

KAMLOOPS - Expect to see roadwork begin in as little as a month as crews prepare to undertake the six-month $10.3-million Overlanders Bridge project. The contract, which was approved by council today, Tuesday, March 10, will include work on the connecting roads, the bridge deck and the west sidewalk. Work on the connecting roads will...

NECESSARY REPAIRS COULD CLOSE MORE BUSINESSES KAMLOOPS - Concerns about traffic flow, loss of business and costs were all aired at an open house discussing the Overlanders Bridge construction project Thursday night but most everyone at the meeting agreed it is a project that needs to be done. Steven Puhallo of the North Shore Business...

SET FOR SPRING CONSTRUCTION KAMLOOPS - Resurfacing of the Overlanders Bridge was originally set to take place in 2014 but when it was realized the sidewalk needed work too the project was put off a year. Now the city is ready to move ahead and will be hosting an open house to share the design...

CONSTRUCTION SET TO START SUMMER 2015 KAMLOOPS - It is a construction project that got a lot of people talking when it was first unveiled and this week the public will get another chance to take a look at the planned changes for Columbia Street before the project begins next summer. In February the city...

KAMLOOPS - If construction this year has been a headache for you, just wait until next year. Major road work is expected to begin on Overlanders Bridge in the spring and then Columbia Street work will begin in early summer. Not a single elector in the city sent in a letter against the $9.3 million...

KAMLOOPS - The city is moving forward on the $9.3 million in repairs needed for the Overlanders Bridge deck and sidewalk, work set to take place in 2015. Originally the project was set to fix the bridge deck at an estimated cost of $6.12 million but early this year staff asked councillors to hold off...

$9.42 M BORROWING BYLAW UP NEXT KAMLOOPS - The entire Overlanders Bridge deck is set to be resurfaced in 2015 and council has agreed to tag on a multi-million dollar attached sidewalk project as well. In January, council agreed to postpone the bridge construction in the hopes of saving funds by completing the two projects...

KAMLOOPS — In an effort to save time, money and stress on area businesses and residents, bridge repairs will just have to wait another year. Council agreed with the staff suggestion a full overhaul of the Overlanders Bridge deck should be put off until 2015 so that proper research can go into the repairs needed...

OVERLANDERS BRIDGE OVERHAUL TO BE PUT OFF ANOTHER YEAR KAMLOOPS – City staff is recommending council put off the full overhaul of Overlanders Bridge until 2015 and instead focus on temporary improvements to the surface this year. The $6.12 million rehabilitation project was approved last year but much needed upgrades to the sidewalk would require...