OTTAWA – Prime Minister Stephen Harper may have accepted the auditor general’s scathing criticism of the troubled F-35 program, but newly released documents show National Defence and Public Works had deep disagreements with Michael Ferguson’s findings.
The final draft of the bombshell report, which accused the departments of hiding the true cost of the multibillion-dollar project and not doing their homework, was the subject of a flurry of letters and protests behind-the-scenes last winter.
As is standard practice, the auditor general’s office shared its report ahead of time with National Defence and Public Works for their review before it was made public.
Internal documents show top bureaucrats fired back.
They didn’t dispute the facts, but disagreed with the auditor general’s conclusions and asked Ferguson to present a more balanced story.
New Democrat defence critic Jack Harris says the contradiction between the public assurances and the private disagreements raises more questions about where the troubled program is headed.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Want to share your thoughts, add context, or connect with others in your community?
You must be logged in to post a comment.