OTTAWA – The Harper government’s much-heralded Arctic patrol ships will cost more to maintain because National Defence won’t be signing a long-term service contract for the mini-icebreakers until the boats are well into construction.
The ships are already 2-3 years behind, according to project schedules, and could fall further behind if contract talks with Irving Shipyard hit a snag.
An internal briefing to former Associate Defence Minister Julian Fantino last fall noted the project was full of financial questions, starting with the actual price tag for building up to eight warships.
The ships, first announced in 2007, were projected to cost $3.1 billion to build and $4.3 billion to maintain over their expected 25 year life cycle.
But the presentation to Fantino shows a decision to “separately compete” the multi-billion dollar in-service contract “after the ships are in build” could have significant implications.
Among other things, the delay in a support contract would “increase the cost of ownership,” and design changes that might be incorporated into the system for ease of long-term maintenance won’t get done.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Want to share your thoughts, add context, or connect with others in your community?
You must be logged in to post a comment.