Canexus crude-by-rail project in Alberta sees costs soar by 40 per cent

CALGARY – Canexus Corp. (TSX:CUS) says the price tag of its oil-by-rail terminal expansion project in Bruderheim, Alta., has risen by 40 per cent over the previous cost estimate of $225 million.

The stock was down about 13 per cent to $6.56 at mid-day on the Toronto Stock Exchange.

CEO Gary Kubera says the company is disappointed with the revised estimate, but noted Canexus has “established a state-of-the-art facility.”

The first phase of the expansion is in the process of starting up and the company expects to load 14 unit trains, or about 30,000 barrels per day of crude, during February.

The project is expected to be complete later this year.

Canexus expects to fund the incremental cost from its committed credit facilities.

News from © The Canadian Press, . All rights reserved.
This material may not be published, broadcast, rewritten or redistributed.

Join the Conversation!

Want to share your thoughts, add context, or connect with others in your community?

The Canadian Press

The Canadian Press is Canada's trusted news source and leader in providing real-time, bilingual multimedia stories across print, broadcast and digital platforms.